PJSC “Sumy NPO” completes the implementation of the contract with the PJSC “Ukrgasdobycha” providing for the supply of separators. Actually, Sumy engineers have already made flare gas separator, which is expected at Abazovskaya of gas complex treatment plant (UKPG), and reached the final stage of production of inlet separator, which should be supplied to Oposhnyanskiy GPP on the first ten days of November.
Gas flare separator, which is a horizontal unit of 7 m length and 5 tons weight, has successfully passed the procedure of hydraulic test, was painted and prepared for shipment.
As for the second sample of the equipment under the order, at the present time it is being tested. This is a thick-walled vertical machine of medium size: its height is about 5 m, weight is about 10 tons, the diameter reaches 1.2 m and its wall thickness is 65 mm.
Both separators to be supplied to Poltava. Phased technical re-equipment of existing facilities of Oposhnyanskiy and Abazovskiy GPP, which are the parts of PJSC “Ukrgasdobycha”, is being carried out.